Fenwick Pier Restoration

Beacon & Vane — Drawing Office

Process

SH 06

Site Inspection Record

Do not scale

Inspection Particulars

Inspection particulars: inspector, date, tide window, and weather, as recorded on site.
InspectorR.V.
Date2026-07-12
Tide window06:40 TO 10:20 · LW 08:15
WeatherOvercast, dry — wind NW, force 3

Condition of Works

SCHEDULED WORKS COMPLETE 60% 39 OF 65 ITEMS · TO 2026-07-12
OPEN DEFECTS 5 2 SERIOUS · 3 MINOR
DAYS TO NEXT INSPECTION 14 HELD FOR 2026-07-26

Schedule of Defects — Open

Schedule of open defects: item, location, defect observed, extent, class, evidence, and action. Serious items are listed first. Item D-01 carries the checker's mark; see the red note below the schedule.
Item Location Defect observed Extent Class Evidence Action
D-01 Checker's mark — see the red note below this schedule Bent P3, pile 3 Cracked pile collar 340 × 3 MM Serious DETAIL A Prop and renew collar
D-02 Walkway bay 7 Handrail bracket corroded 30% Serious DETAIL B Renew bracket and bolts
D-03 Deck bay 12 Deck boards sprung at fixings 2 NO Minor Refix boards
D-04 Ladder L2 Bottom rung worn 1 NO Minor Renew rung
D-05 Lamp housing Lens glass crazed Minor Renew lens at next visit

D-01 cracked pile collar — prop bent P3 before next high water.

Site Evidence — Details of Recorded Defects

Details A and B — recorded defects at D-01 and D-02 Two line details traced from site photographs. Detail A: a pile at bent P3 with its collar drawn as a rectangle; a crack runs 340 millimetres across the collar, 3 millimetres open at its widest, dimensioned below. Detail B: a handrail bracket 480 millimetres long fixed to a wall face; its outer end carries a hatched zone marking 30 percent section loss, and its two M12 by 180 bolts are seized. HW LEVEL 340 MM 480 MM CRACK 3 MM OPEN SECTION LOSS 30% M12 × 180 BOLTS SEIZED DETAIL A — CRACKED PILE COLLAR, BENT P3 DETAIL B — CORRODED BRACKET, BAY 7
DETAILS A AND B · TRACED FROM SITE PHOTOGRAPHS BV-P-118 AND BV-P-121 · NTS · DO NOT SCALE

Record of Inspections

Record of inspections: date, inspected by, position, and open defects at each visit. A recorded inspection is appended to this schedule.
Date Inspected by Position Open defects
2026-05-30 E.H. Resident engineer 7
2026-06-20 R.V. Clerk of works 6

Sign-Off

Next Inspection

No Entry Made — This Region Held for the Next Inspection

Beacon & Vane, Drawing Office · Fenwick · Set BV-12 · Sheets held in the office window for inspection